IMG_20240225_104214.jpg

Project Overview

The client's FPSO was in dry dock in Dubai and had to sail away in a few days but some equipment was yet to be fixed. We sent a 3 field specialists to install C-CLAWs and train the onboard crew. Overall, hundreds of C-CLAWs S300 were installed in a few days, and the job continued during the sail-away thanks to the training provided to the onboard crew.