FPSO DECK REPAIR WITHOUT HOT WORK 

LOCATION : 

Angola - offshore

KEY WORDS :

Coldshield - No hot work - Structural repair

MARKET :

Offshore & Marine

IMG_1462.JPG

JOB DESCRIPTION

We completed a structural repair on the deck of a TotalEnergies FPSO that was suffering from severe steel thinning. Together with the client, we co-developed and implemented ColdShield, a cold-applied sandwich system, working directly with the onboard crew to restore the deck’s structural integrity.
Because the solution required no hot work, the repair was carried out safely during ongoing operations, avoiding any production shutdown. As a result, TotalEnergies estimated a saving of 100,000 barrels per day over 60 days.